Land Feasibility Study for Development: Checklist and Cost
What a land feasibility study tests, who does it, how long it takes and published cost examples, with a land development feasibility checklist.
A land feasibility study tests whether a specific project, such as a 40-lot subdivision, can be approved, served, built and paid for on a particular site. A buyer usually runs it after a first screen and before committing to the purchase. An owner can also commission one before developing land already held. The buyer or owner leads it with an engineer, surveyor and other specialists. The result is a written go, revise or stop decision.
Pillar, a land research platform, wrote this guide for land buyers, small developers and acquisition analysts. Agency rules and fees come from the agencies' own pages, checked November 11, 2026. It is general information, not legal, engineering or investment advice for a specific site.
What is a land feasibility study?
A land feasibility study starts with a defined proposal. "What could go here?" is a screening question, and our desktop site screen covers it. "Can we build 40 single-family lots here, with this entrance and this sewer connection, at this land price?" is a feasibility question.
The study asks three things about that proposal:
- Can it be approved? Zoning, subdivision rules and the review path.
- Can it be built and served? Access, utilities, flood, wetlands, soils, survey and title.
- Does it pay? Lot yield, development cost, sale prices and the land price.
Matt Twomey, president of a Pennsylvania construction firm, described the same purpose in Area Development in November 2006. Owners and developers run feasibility studies "before buying land or building on an existing site" to learn whether the site will work, whether the project is "financially feasible" and "whether the locale's regulatory structure will allow it."
The study ends in a decision: go ahead, revise the plan, renegotiate or stop. "Land development feasibility study" and "land development feasibility analysis" mean the same work in this guide.
What does a land development feasibility study include?
Most studies cover eight workstreams:
- Parcel identity and acreage
- Zoning and entitlements
- Access
- Utilities
- Flood, wetlands, soils and other site conditions
- Survey and title
- Concept plan and yield
- Market and cost
How deep each one goes depends on the project. Twomey writes that even a small study reviews "the client's needs, topography, and government ordinances." Larger ones add site drawings, preliminary plans, a statement of probable cost, a preliminary schedule and any offsite improvements the municipality requires (Area Development).
For one homesite the list is shorter. Stennes Homes, a home builder in Puyallup, Washington, describes its study as legal access, zoning restrictions, wetland and habitat checks, water or well, utility connections, HOA requirements, a preliminary site plan and a written report.
Land development feasibility study checklist
Copy this list into your deal file. Beside each question, write the answer, its source and the date you checked it. Leave a question marked open until a record or a named professional answers it.
1. Parcel identity and acreage
- Which parcels are in the deal?
- Source: the deed's legal description, matched to the county parcel record by parcel number.
- Guide: land assemblage parcel record.
- Which acreage figure does the plan use?
- Source: the deed, the county GIS record and the survey, each kept under its own label.
- Guide: deeded acres vs. GIS acres.
- Which city or county regulates the site?
- Source: the official boundary map and the planning office, not the mailing address.
- Guide: desktop site screen.
2. Zoning and entitlements
- Does current zoning allow the use, lot size and density you plan?
- Source: the adopted zoning map and code text, then a written answer from planning staff.
- Guide: R1 zoning in ten codes.
- Does the plan need a rezoning, variance or other discretionary approval?
- Source: planning staff, the future land use map and a land use attorney.
- Guide: zoning vs. future land use.
- Which applications are required, in what order, and who decides each one?
- Source: the jurisdiction's subdivision and site plan procedures, and a pre-application meeting (examples below).
- If the seller says the site is approved, what do the documents cover?
- Source: the agency's case file. See "What an approval actually covers" below.
3. Access
- Is there legal access, not just a road beside the parcel?
- Source: recorded deeds, plats and easements, and the title commitment.
- Guide: road frontage vs. legal access.
- Will the road agency permit the entrance the plan needs?
- Source: the city, county or state driveway permit office, and a traffic engineer if a study is required.
- Does any lot reach the road by a narrow strip?
- Source: the survey, recorded plat and concept plan for the lot's shape, then the local flag lot and fire access rules for whether that shape is allowed.
- Guide: flag lot rules.
4. Utilities
- Who provides water, sewer, power and gas at this location?
- Source: each provider's service area map and staff.
- Will each provider serve this project, and on what conditions?
- Source: a written response that names the project and the unit count. A nearby line is not an answer.
- Guide: will-serve letters.
- If there is no sewer, will the soil support septic systems?
- Source: the local health department and a site evaluation or perc test.
- Guide: perc tests.
5. Flood, wetlands, soils and other site conditions
- Which flood zones touch the site, and on which map?
- Source: FEMA's flood maps and the local floodplain administrator. Note whether the map is effective, preliminary or historic.
- Guide: flood Zone X.
- Are there wetlands or streams on the site?
- Source: the National Wetlands Inventory for a first look. It does not establish regulatory jurisdiction, so a wetland consultant sets the boundary in the field.
- Guide: wetland delineation.
- What limits do the mapped soils suggest?
- Source: the USDA Web Soil Survey, then a geotechnical engineer for borings on the site.
- Guide: soil survey investigation brief.
- Could protected species or habitat affect the plan?
- Source: the U.S. Fish and Wildlife Service's IPaC planning tool, then a qualified biologist.
- Is there any sign of past contamination?
- Source: a Phase I environmental site assessment by an environmental professional (EPA).
- How steep is the land, and where does stormwater go?
- Source: a topographic survey and the civil engineer.
6. Survey and title
- Is there a current boundary survey, and does it match the deed and the title commitment?
- Source: a licensed land surveyor, working from the title commitment.
- Guide: ALTA surveys.
- Which easements, covenants and other exceptions burden the land?
- Source: the title commitment and every recorded document it lists, read with a real estate attorney.
- Guide: easement vs. right-of-way.
7. Concept plan and yield
- How many lots or units fit once roads, drainage, open space and setbacks are drawn?
- Source: a concept plan by a civil engineer or land planner, drawn on a stated boundary with the code's dimensions.
- What does each layout assume?
- Source: your own scenario record of the boundary, acreage basis, lot dimensions and land set aside. A changed layout gets a new name. When the proposal changes, recheck whether earlier staff answers, service letters and cost estimates still cover it.
- What did the jurisdiction say about the layout?
- Source: notes from the pre-application meeting.
Do not subtract mapped constraints from gross acres and call the result buildable. Overlapping layers can count the same ground twice.
8. Market and cost
- What will finished lots or homes sell for, and how quickly?
- Source: closed sales and competing projects, from a broker or market analyst. Keep asking prices apart from closed sales.
- Guide: reading a local supply pipeline.
- What will it cost to entitle and develop the site?
- Source: the engineer's opinion of probable cost, agency fee schedules and contractor quotes. Record what each figure excludes.
- Does the land price still work?
- Source: a pro forma run on the same scenario as the concept plan. An unpriced item stays marked unknown, not zero.
What is a pre-application meeting? Five real examples
Many cities and counties will look at a concept before you file an application. The name, fee and scope differ in each place. These five were checked November 11, 2026.
- Pinellas County, Florida: Site Plan Pre-Application Meeting
- Fee: $350, credited toward the site plan submittal.
- You submit: a survey and a concept plan drawn to scale, a narrative with your questions, and notes on floodplain, stormwater, utilities and wetlands.
- What it decides: nothing. Staff comments are "solely for preliminary informational purposes" and are not "an approval, denial, or agreement to approve or deny any development order."
- Portland, Oregon: Early Assistance
- Fee: for zoning and infrastructure review, $4,306 for written information or $6,175 with a meeting. A request that involves a street vacation costs $5,244 or $7,710. Zoning only is $1,533 or $1,850 (fee schedule effective July 10, 2026).
- You submit: the application form, a written project description and site plans drawn to a measurable scale, plus building elevations where appropriate. The zoning-only meeting about residential infill options needs no site plan.
- What it decides: nothing. The city calls these "informational-only meetings". One does not replace the pre-application conference required before Type III and Type IV land use reviews. If the proposal changes in scope or layout after the summary report, you must request another review to get answers.
- King County, Washington: Pre-application Meeting
- Fee: $1,452 for each review staff member, effective January 1 through December 31, 2026. A voluntary meeting always includes a planner, plus the review disciplines you select. A mandatory one needs at least two to three staff members, and a larger scope can add more. The meeting does not include follow-up review or design questions afterward.
- You submit: a detailed project narrative, specific questions, a Site Areas Worksheet and a site plan. Subdivisions add a Residential Density Worksheet.
- What it decides: nothing. The process is "NOT INTENDED TO PROVIDE ASSURANCES THAT A DEVELOPMENT PROPOSAL WILL BE APPROVED" and does not vest a proposal to a version of the code.
- Phoenix, Arizona: Fact Finding and Pre-Application Meeting
- Fee: fact finding is $390 for a written response or $780 with a staff meeting. The initial pre-application meeting is $1,560 (fee schedule effective January 20, 2026).
- You submit, for fact finding: the address, parcel numbers, proposed type of development and your questions. This form is for sites outside the Downtown Code and Walkable Urban Code areas, which use a separate checklist.
- What it decides: fact finding answers only the questions submitted. Staff "will not conduct a complete review of a proposed site plan", and it "does not replace the required pre-application meeting." Phoenix adds that "small commercial or industrial projects may not require a pre-application submittal", so ask staff which applies.
- Austin, Texas: Subdivision Project Assessment
- Fee: the page gives no amounts. The city invoices Completeness Check fees first, then formal review fees once it accepts the formal application.
- You submit: a Completeness Check application, then a formal application with the certification letter. The letter expires 45 calendar days after it is issued. Submit the formal application and pay its review fees before then, or start a new Completeness Check.
- What it decides: it gives "a high-level evaluation of the potential code compliance of a future subdivision application" and "a 180-day binding staff recommendation on any discretionary approvals." Those recommendations apply only if a subdivision application is accepted for review within 180 calendar days of the report. A subdivision application still has to follow.
None of the five pages describes its meeting as an approval. Published fees start at $350 and reach several thousand dollars. Look up your own jurisdiction's version before an engineer draws anything final.
Who does a land feasibility study?
The buyer or developer runs the study and makes the decision. No single profession covers all of it. The work is usually split like this:
- Civil engineer or land planner: concept plan, grading, drainage, utilities and cost.
- Land surveyor: boundary, topography and what crosses the land.
- Land use attorney or planner: zoning, approvals and conditions.
- Title company and real estate attorney: the title commitment and recorded documents.
- Environmental professional: the environmental assessment. EPA says many of its steps must be done by or under one (EPA).
- Wetland, soil and geotechnical specialists: field boundaries and borings.
- Broker or market analyst: prices and sales pace.
Twomey's advice: "Involve a builder, architect, and engineer in your feasibility study, rather than depending on just one discipline" (Area Development).
Agency staff answer questions. They do not do the study. King County says its meeting is not "a feasibility study based on varying scenarios" (King County).
How long does a feasibility study take, and what does it cost?
There is no standard duration or price. These are the figures we found with a named source.
Time
- Twomey, writing about commercial and industrial projects in 2006: "Expect a feasibility study to take about 60 to 90 days" (Area Development).
- Suprema Homes, a home builder in Tacoma, Washington, recommends that a land offer "include a minimum 30-day but preferably 45-day contingency for a feasibility study."
- Agency calendars set a floor. Portland says early assistance meetings "are usually held within three weeks of request." Phoenix gives about two weeks for a written fact finding response and about three weeks to schedule a meeting.
- Environmental work expires. EPA says all appropriate inquiries "must be conducted or updated within one year before the date of acquisition", and some parts within 180 days (EPA). Order it too early and you may pay for an update.
Cost
- Stennes Homes, the Puyallup, Washington builder, publishes a price of $1,800 to $2,300 for its single-property study. The page is undated. The price includes up to five hours of property research. The company gives an estimate, and the client agrees to the cost, before work starts. It reserves the right to bill further research at $125 an hour after notifying the client. Outside consultants are extra (Stennes Homes).
- Twomey's 2006 figure for commercial projects is "anywhere from a few thousand to tens of thousands of dollars", and rarely "more than one percent of overall project costs" (Area Development). It is old and it is not about subdivisions.
- We found no current, sourced figure for a subdivision-scale study. Other pages quote ranges without saying where they come from, so we left them out.
Cost depends on scope. The main drivers are:
- The number of acres, parcels and owners.
- Whether the plan needs a rezoning or another discretionary approval.
- Which field studies the site needs: survey, wetland delineation, soil borings, environmental assessment, traffic study.
- How far the engineer takes the concept, and how many layouts you test.
- Agency fees, such as the pre-application fees above.
Ask each consultant for a written scope and fee before work starts. For sourced prices and turnaround on single studies, see our guides to ALTA surveys, wetland delineations and perc tests.
Feasibility study vs. due diligence
People use the two terms loosely, and each contract defines its own. They overlap. A desktop screen and a feasibility study can both be part of a buyer's due diligence:
- Desktop screen. Asks whether a site deserves more work. Our land due diligence checklist covers it.
- Feasibility study. Tests one defined project against the site. That is this guide.
- Purchase due diligence. Everything the buyer investigates before closing. It can include the screen and the study, and it adds what the purchase itself needs, such as financing, title insurance and the contract terms.
The North Carolina Real Estate Commission describes due diligence under that state's standard residential contract as "the buyer's opportunity to engage in a process of further investigation of the property and the transaction" within a period the buyer and seller agree on (NCREC bulletin, February 2014). Its examples include inspections, a survey, an appraisal, a title search and loan qualification. That is wider than feasibility, which asks only whether the project works.
Twomey's article calls the feasibility study "a smaller investment" to make before spending on due diligence. It also says any land agreement signed during the study should "include a reimbursement of your deposit should you elect not to pursue the project" (Area Development).
What goes in a land feasibility report?
A reader who was not involved should be able to check the conclusion. Include:
- The proposal tested: product, lot count, access point and utility plan.
- The parcel record: identifiers, jurisdiction, boundary source and acreage basis.
- Findings for each workstream, each with its source and the date checked.
- The concept plan and the assumptions behind it.
- The approval path: applications needed, who decides each and a preliminary schedule.
- Cost and revenue figures, with who supplied each and what it excludes.
- Open questions, each with an owner and a next check date.
- The decision, and the evidence that would change it.
Our feasibility worksheet is a plain-text template for this record. Keep it with the screening worksheet from the earlier stage.
What a feasibility study does not do
- It is not a survey. A licensed surveyor locates the boundary and what crosses it. See ALTA surveys.
- It is not a title commitment. The title company's commitment lists the recorded matters it excepts from coverage. See where to find them.
- It is not an environmental assessment. EPA says the results of all appropriate inquiries go in a written report signed by an environmental professional (EPA).
- It is not an approval. Only the jurisdiction approves a project. The next section covers what an approval does and does not include.
What an approval actually covers
When a seller says a site is approved, ask for the documents. A preliminary plan approval, an approval to record a plat, a recorded map and a construction permit answer different questions, and one approval may not unlock the next. Austin says a subdivision "is not a site plan or building permit and does not authorize the construction, demolition, or relocation of buildings or any site construction" (City of Austin).
Raleigh, North Carolina shows the gap. Its preliminary subdivision review ends in an Administrative Approval letter "containing conditions of approval." Its recorded map review gives "approval to record the plat", and the plat must be recorded "on or before the 14th day following the certification of the review officer." Approval to record and recording are separate events. Those are Raleigh's rules, checked November 11, 2026. Look up your own jurisdiction's.
Log each document in an approval-evidence register, one row per document:
- The seller's claim, kept apart from the agency document's exact title and status.
- The agency, case number, document date, plan revision, parcels and phase covered. Lot counts stay attached to that document.
- Each condition and the milestone it applies to, with evidence that it was met. An analyst's assumption does not close a condition.
- The approval to record, kept apart from the recording reference, date and map copy you inspected.
- The source URL, page or sheet, and date checked. If you cannot find a document, list where you looked. Do not write that it does not exist.
- Open questions about scope, validity, revisions or construction permission. Assign each to a planner, surveyor or engineer, with a next check date.
The feasibility worksheet includes this register.
A worked example: "approved" for 50 lots
This example is fictional. The documents, identifiers and lot counts are invented.
A seller's packet says a 50-lot proposal is approved. It holds two documents:
- E1: a preliminary approval that references drawing R2. Phase 1 has 20 proposed lots and Phase 2 has 30. One condition ties drainage to a later construction-plan review.
- E2: a recorded map, reference SIM-MAP-01. It covers Phase 1 only, lots 1 to 20.
Nothing in the packet shows that the drainage condition was met, that Phase 2 was recorded or that construction is authorized in either phase.
Enter E1 and E2 as separate rows. The sum 20 + 30 = 50 reconciles the labels. It does not establish 50 recorded or buildable lots. Mark the missing evidence as absent from this packet, with agency and recording searches still to run.
Then hand off three tasks. The planner checks whether E1 still applies and what its conditions require. The surveyor reconciles the recorded map with the boundary being bought. A named reviewer obtains the construction authorization. The decision stays on hold until those come back.
A second example: a scenario is not a decision
This one is fictional too. A team's parcel record shows 24 gross acres with the boundary unverified, and two sketches labeled "A: 72 lots" and "B: 60 lots". Utility service and access are unconfirmed, and the cost note leaves both out. That supports a service inquiry, an access review and an engineer's check of each concept's inputs. It does not support reporting 72 saleable lots or treating the cost note as a budget.
Where Pillar fits
Pillar helps with the early research, not the professional work. Its map layers show zoning, floodplain, wetlands, utilities, roads, city limits and future land use over parcel boundaries. Coverage and plan access vary by dataset. Pillar does not supply a concept plan, a survey, an engineering plan or an entitlement approval.