Build to Suit: How the Deal Works From the Land Side
Build to suit means a developer builds or expands a facility for a specific tenant. See terms from three filed leases and site checks before an offer.
Build to suit (BTS) is a commercial real estate arrangement in which a developer or landlord builds a new facility, or expands an existing one, to a specific tenant's requirements for a long-term lease. In the three filed leases below, the parties signed the lease before the new facility was built.
Pillar, a land research platform, wrote this guide. Sources were read November 23, 2026; verify current text. This is general information, not legal, tax or accounting advice. Confirm deal terms and local rules with a licensed professional in your state.
What is build to suit?
The NAIOP Research Foundation's April 2024 glossary defines build-to-suit by its design for a specific tenant. In W. P. Carey's account, a developer or investor funds and manages construction or expansion to meet that tenant's specifications.
How does a build to suit work? Six steps from the land side
- The tenant's site criteria. Start with the tenant's requirements for lot size, frontage, access, traffic, zoning and utilities. Most of O'Reilly Auto Parts' growth comes from building freestanding stores on land it owns. It also considers build-to-suit, ground leases and building leases. Its freestanding prototype typically needs 30,000 to 35,000 square feet of land.
- The site search and first screen. Turn the criteria into filters (acreage, frontage, zoning category, traffic count) and run each candidate through the checks below. See retail site selection.
- Site control before the lease. Decide how to control land you do not own and what happens if you cannot secure it. For federal new-construction leases, the US General Services Administration's (GSA) 2018 guide calls a purchase option binding on the owner upon exercise the most common alternative to deeded ownership. Leasehold control may suffice if the project can proceed as intended.
- Entitlements and permits. MACOM's lease lists what its landlord had to pursue, "if and as applicable: zoning variance(s); site plan approvals; special permit approval(s)"; the list goes on to drainage, off-site easements, utilities, access, wetlands or environmental permits, and subdivision. See the entitlement process, conditional use permits and traffic impact studies.
- Land closing, construction, delivery and rent. In the three filed leases below, base rent ordinarily started at completed delivery or substantial completion. If work was substantially complete before the approved updated date, MACOM could defer possession to that date unless it agreed in writing to an earlier date. Deemed possession after an approvals failure triggered $1 annual base rent. If tenant delay pushed the Iowa lease's commencement past its target date, rent started on the date it would have started without that delay. The landlord still had to finish the work (§ 2.5). The leases allocate project costs separately from base rent; MACOM, for one, could pay its share of project costs before rent began.
- Sale to a net lease investor, if planned. W. P. Carey says a developer-led build-to-suit often involves an investor "as a capital partner to either finance the construction or acquire the building upon completion."
What real build-to-suit leases say
These three nonretail lease exhibits illustrate individual deals and are publicly available in EDGAR.
1. The landlord still had to buy the land (North Carolina, 2021). Lease dated June 11, 2021 to Cygnus Technologies, LLC, filed as Exhibit 10.18 to Maravai LifeSciences Holdings' Form 10-K on Feb. 29, 2024.
- Land. The landlord had to acquire fee simple title and start its work within 30 days after the building department with jurisdiction issued a building permit. If it had not done both by the lease's construction commencement date (150 days after signing if the tenant supplied the necessary plan information within 30 days), force majeure aside, the tenant could terminate by written notice effective in 60 days. The notice became void if the landlord gave reasonably sufficient written evidence of both steps within that period (§§ 6(A), 36). The first physical alteration counted as commencement only if the landlord kept pursuing meaningful progress. To claim a force-majeure delay, a party had to notify the other in writing within 10 days of first learning of the event likely to cause the delay.
- Approvals. The landlord had to secure required zoning approvals at its cost and, before starting construction, deliver a town zoning letter confirming that the zoning permits the tenant's intended use (§ 5(A)).
- Delivery. The landlord owed completion by the date in its 30-day notice, with an outside limit of 360 days from signing that force majeure could not extend (§§ 6(C), 36). Missing the outside date let the tenant terminate by written notice. If completion ran more than 30 days past it, the lease credited one day of base rent for each day from the outside date to completion.
- Rent, term and overruns. Rent started when the landlord delivered the premises with its work completed, at $25.00 per square foot of rentable area in the first lease year, rising 2.5% a year (§ 9(A)). The initial term was 10 years with four 5-year options, subject to conditions (§ 8). The landlord paid for the shell. On completion of the required tenant improvements and delivery, the tenant had to reimburse the landlord's actual costs for those improvements above the tenant improvement allowance. The landlord had to provide a detailed itemization and receipted bills (§ 6(D)).
2. A tenant affiliate sold property to the landlord (Massachusetts, 2016). Lease dated Dec. 28, 2016, filed as Exhibit 10.2 to MACOM Technology Solutions Holdings' Form 8-K on Jan. 5, 2017. The 8-K reports that a wholly owned MACOM subsidiary sold property to the buyer. MACOM signed a separate 20-year build-to-suit lease for a new facility as part of that transaction.
- Rent on cost and overruns. Absent an approvals failure, initial annual base rent was $1,278,750, calculated as 7.75% of a $16,500,000 "Rent Baseline" (§ 3(a); Appendix 1). Under that schedule, base rent rose 1.5% after the initial term's first 12 full calendar months and annually thereafter. Each extension reset under § 3(b) and followed the same increase schedule. Subject to the lease's exceptions, the tenant was responsible for the project budget above the baseline, and the landlord for increases in the cost of its work above the then-approved budget (Appendix 1).
- Approvals. If the landlord determined despite diligent, good-faith efforts that it could not obtain final approval before the first anniversary of the lease's effective date, it had to give written notice by five business days after that anniversary. The tenant could elect in writing to pursue final approval at its own expense within 20 business days after that notice, or within 20 business days after the anniversary if approval was still missing then, even without notice. Appendix 1 sets the pursuit period and any extension. Possession was deemed to occur if the tenant missed its election window or if, after a timely election, final approval still had not occurred by the applicable extended deadline. The landlord then had no duty to build, the tenant's Appendix 1 payments fell away, and Exhibit F set base rent at $1.00 a year for the whole term, extensions included. Neither party could terminate for that failure, and the tenant could, as far as the lease otherwise permitted, secure approvals and build itself (Appendix 1; Exhibit F).
- Delivery and term. The preliminary schedule anticipated possession on or before Aug. 1, 2018. The abatement clock used the earlier of the updated anticipated possession date and the estimated substantial-completion date in the landlord's 30-day notice. Appendix 1 allows both dates to move for tenant delays, change orders or force majeure, with only one force-majeure extension of the date in that notice. Past that deadline the tenant's sole remedy was abatement of 150% of daily base rent for each of the first 30 days and 200% for each day after that (Appendix 1). The initial term ran about 20 years from commencement, with two 10-year options, subject to conditions (§ 2).
3. The lease was contingent on the land closing (Iowa, 2007). An older Net Lease Agreement (Build-to-Suit) dated Nov. 13, 2007 to TPI Iowa, LLC, filed with later amendments as Exhibit 10.11 to TPI Composites' Form S-1 on June 17, 2016. Two terms from the lease as originally signed:
- Land. The lease was "contingent on Landlord acquiring the fee simple title to substantially all the land" shown on its Exhibit A, and the landlord agreed not to buy before the tenant's written notice to proceed. If either step was still outstanding after Nov. 15, 2007, a date not subject to force majeure, either side could terminate by written notice before both occurred (§ 20.28).
- Rent on cost. Initial annual basic rent "shall equal 9% of the" lease's Total Project Costs, which included the land's purchase price and closing costs, net of developer grants received under a local redevelopment agreement (§ 3.1; Exhibit D). Above $13.5 million net of grants, the lease based rent on $13.5 million and required the tenant to pay the excess within 30 days of demand, subject to an option to include up to $600,000 in the rent basis. The option covered original improvements in the final plans and tenant change orders consistent with the plans before each change (§ 3.1).
Accounting. FASB's leases standard applies its sale and leaseback subtopic "If the lessee controls the underlying asset being constructed before the commencement date" (paragraph 842-40-55-5, as issued in ASU 2016-02). Ask your accountant how a structure fits the current standard.
Build to suit vs. spec, ground lease, sale-leaseback and tenant improvements
- Speculative ("spec") development. NAIOP: "A building developed and constructed without any preleasing in place."
- Ground lease. Attorneys' Title Guaranty Fund describes "a long-term lease of land only," under which the tenant "usually is required to construct a building or maintain and use current improvements on the land as specified in the lease." See ground leases.
- Sale-leaseback. NAIOP: "An owner-occupied property that is sold to a third-party investor. The previous owner becomes the tenant that pays rent to the new owner."
- Tenant improvements in an existing building. GSA's Pricing Desk Guide (5th edition, effective Aug. 1, 2020) defines them as "the finishes and fixtures that typically take space from the shell condition to a finished, usable condition."
What is a reverse build to suit?
Published sources use the term differently. FBT Gibbons uses the term when a tenant develops and builds out the leased property for its use. REICounsel uses it when a tenant owns or controls the land and a developer builds on it.
Ask who holds title and who builds and funds the work.
Government build to suit: GSA leases involving new construction
GSA's 2018 desk guide describes what we read as two federal counterparts. Lease Construction is relatively rare and applies when GSA mandates new construction as the only way to meet its technical requirements. In Market Driven Construction, GSA typically seeks existing space, but new construction may be offered if no existing building meets the government's requirements. GSA still hosts the chapter. Its leasing templates page (updated Sept. 18, 2026) omits it.
Under the default May 2026 R100 template, an offeror whose property does not comply must submit a plan and schedule showing how it will obtain all necessary zoning approvals before construction and how long that will take (§ 3.01(E)). A template note lets the contracting officer instead require compliance before lease award. GSA says its templates are for reference and that the active solicitation and its amendments control.
Build-to-suit land: what to check before an offer
- Legal lot and acreage. Start with the recorded plat and deed, not a listing, and check the acreage against the tenant's range. Ask the local subdivision authority to confirm legal lot status if the records leave it unclear. See outparcels and pad sites.
- Zoning for the use and the drive-through. Read the use table and use-specific rules for the parcel's actual district and overlays. In Tulsa's zoning code (as amended and effective Oct. 26, 2026), Table 15-2 lists Restaurant as "P" in the CS, CG and CH districts (see Section 40.330) and "Drive-in or Drive-through Facility (as a component of an allowed principal use)" as "P" there but "S" in OL, OM and CBD (see Section 55.100). Under Section 15.020, "P" means permitted as of right in the district. "S" means a use may be allowed after special exception review and approval under Section 70.120. Both are subject to the supplemental rules in the table's final column and all other applicable code rules. Table 15-2 note [1] permits restaurants as accessory uses in OL, OM and OMH only within the principal office building, occupying no more than 5% of its floor area. Table 20-1 marks the drive-in or drive-through use "X" in all three River Design Overlay districts, and § 20.050-B says uses so marked are "expressly prohibited" there. See commercial zoning.
- Access and frontage. Frontage does not guarantee a driveway permit. See road frontage vs. legal access and, for industrial users, truck access.
- Traffic counts. Compare the published count on the fronting road with the tenant's minimum. See AADT traffic counts.
- Flood zone and wetlands. Check FEMA's Flood Map Service Center and the Fish and Wildlife Service's Wetlands Mapper, whose FAQ says there is no attempt "to establish the geographical scope of the regulatory programs of government agencies" and refers readers to federal, state or local agencies, including the Army Corps of Engineers.
- Utilities. A mapped line does not confirm capacity. See will-serve letters.
In the deal documents. The due diligence period and approval contingencies are negotiated in the option or purchase contract (entitled vs. unentitled land). Order a title commitment and an ALTA survey early in due diligence.
For a first pass, open the parcel in Pillar for its available zoning facts and acreage and turn on mapped FEMA flood zones (Pillar for retail).
Quick answers
What does build to suit mean? A developer or landlord builds or expands a facility for a specific tenant's long-term lease.
Who buys the land in a build to suit? It depends on the deal. In the filed leases above, one landlord had to buy the land after signing, one lease was contingent on the landlord acquiring it, and in one the tenant's affiliate sold property to the landlord.
How long is a build-to-suit lease? The term is negotiated. Two filed leases started at 10 and about 20 years, plus extension options. W. P. Carey cites 10–30 years.
How is build-to-suit rent set? The parties negotiate it. The filed leases used a rate per rentable square foot, a percentage of a fixed baseline, or a percentage of defined project costs, subject to adjustments.
When does rent start on a build to suit? Usually at completed delivery or substantial completion in these leases. See step 5 for exceptions.
How long does a build to suit take? W. P. Carey says "anywhere from 12-36 months depending on the size, location, permitting and other specifications."
What is the difference between build to suit and spec? NAIOP defines spec as building without preleasing and build-to-suit as designing for a specific tenant.