Traffic Impact Study: Thresholds, Scope and Review Fees

Traffic impact study requirements, report scope, California VMT rules, and agency review fees. Learn what to check before making an offer on land.

Pillar team12 min read

A traffic impact study—or traffic impact analysis (TIA)—is an engineering report usually prepared by a licensed engineer for agency review. It projects added development trips, evaluates nearby road effects and recommends improvements.

By Pillar, a land research software company. Sources read November 22, 2026; verify current text. Not legal or engineering advice—confirm rules with a licensed engineer, planner or attorney.

When is a traffic impact study required?

Florida DOT

  • Thresholds: Under Fla. Admin. Code R. 14-96.004 and 14-96.005 (eff. April 2, 2023), study rules cover standard Category C–G applications from 601 projected average vehicle trips per day (VTPD) site-generated (unadjusted for roadway diversion, 14-96.002(38)), plus any application requesting or requiring a new signal, new/modified median opening or auxiliary lane (14-96.005(5)).
  • Process and seal: Category C–G applicants must request a no-fee advisory pre-application meeting (14-96.005(1)(a)); Category C (601–1,200 VTPD) is exempt from some listed items if the applicant shows they have no significant bearing on permitting (14-96.005(6)). Except cursory analyses, a Florida Professional Engineer (PE) signs, dates and seals the study (14-96.005(5)).
  • Redevelopments: Fla. Stat. § 335.182(3)(c) (amended 2025) defines "significant change" as a change in property use (including developing land, structures or facilities) or an expansion of property, structures or facilities that increases peak-hour or daily trips >25% and >100 vehicles/day over existing use. Owners expecting added traffic from expansion or redevelopment must contact FDOT to determine if a new application and connection modifications are required. If FDOT finds that the increase constitutes a significant change, it requires a new permit application (14-96.005(2)(a)). Separately, 14-96.002(32) (citing pre-2025 § 335.182(3)(b)) requires no new application if FDOT finds added traffic needs no modification to existing permitted connections.

Virginia DOT

  • Scope: Chapter 155 covers comprehensive plans (24VAC30-155-30) and rezonings (24VAC30-155-40; Va. Code § 15.2-2222.1; -50 repealed 2011). Under -40(A)–(B), localities submit qualifying rezoning packages within 10 business days of a complete application, with a local traffic impact statement or, if VDOT has not certified local requirements, a VDOT traffic impact statement (VTIS).
  • Triggers: Where VDOT maintains secondary roads, the trigger is more than 5,000 vehicle trips per day at the site's state-controlled highway connection, combining volumes across multiple highway entrances. If the site has no direct entrance to a state-controlled highway, measure where its connecting road network joins one. Where VDOT does not maintain local roads: >5,000 VTPD with nearest property line within 3,000 feet along public roads of a connection to a state-controlled highway. Residential rezonings: >400 VTPD on a state-controlled highway where assigned trips exceed its latest published VDOT or locality count (per receiving highway).
  • Math and exemptions: Trigger calculations use Institute of Transportation Engineers (ITE) Trip Generation (8th Ed., 2008) without internal capture; removed existing-use trips may be deducted. No submission to VDOT is required under -40 if allowable uses stay unchanged, or if maximum daily trips drop with no increase in maximum adjacent-street AM/PM or weekend peak-hour trips versus by-right zoning (except governmental uses like schools and libraries). See -40(C)(1) for small-area-plan reuse.

Maricopa County, Arizona

  • Triggers: Under the Maricopa County Department of Transportation (MCDOT) Traffic Impact Study Manual (eff. June 25, 2025, § 1.2.1), a full traffic impact study (TIS) is required for county-jurisdiction new or modified developments at 100 or more trips in either the morning or afternoon peak hour, typically on Special Use Permits, Plans of Development, Military Compatibility Permits, preliminary plats and building permits (site plans, improvement plans, access requests; entitlement and preliminary-plat requirement/scope set at pre-application or submittal). Table 1, note 1, counts all proposed uses without subtracting prior-use trips for net change, or "new" trips.
  • Below 100 and waivers: Smaller projects generally need a Traffic Statement (TS) (§ 1.2.2), though MCDOT's Transportation Systems Management and Operations (TSMO) Division may require a full TIS for known safety/operational concerns, possible or perceived adverse effects on adjacent neighborhoods or sensitive uses, geometry needing review from adjacent-improvement timing, or county-identified problems the project could aggravate (§ 1.2.1). TSMO may waive a TS (not a TIS) if a written request shows no significant impact (driveway-spacing map, trip generation, immediately adjacent road counts within one year before submittal, no-adverse-impact conclusion) meeting at minimum four criteria: <5 average AM or PM peak-hour trips; no requested state-highway or county-arterial access; existing and proposed traffic averages no more than 150 vehicles per day on any unpaved road; no current traffic problems or local concerns (§ 1.2.3).
  • Certification (§ 2.4): An Arizona-registered civil PE must supervise every TIS, TS and waiver request, and sign and seal the final TIS or TS.

In Texas's municipal subdivision subchapter (Ch. 212, Subch. A), Tex. Loc. Gov't Code § 212.004(g) (eff. September 1, 2023) bars municipal governing bodies or plat authorities from requiring an analysis, study, document, agreement or similar item in a plat, development-permit or subdivision application unless explicitly allowed by state law. It does not name traffic studies; ask Texas counsel how it applies to a city's traffic-study requirement.

California's shift to vehicle miles traveled (SB 743)

California shifted California Environmental Quality Act (CEQA) transportation review from automobile delay to vehicle miles traveled (VMT) via Senate Bill 743 (2013), codified in Cal. Pub. Res. Code § 21099 (amended eff. January 1, 2020) and implemented by CEQA Guideline 14 CCR § 15064.3 (operative December 28, 2018; prospective under § 15007; immediate election allowed before statewide application July 1, 2020, (c)).

Under § 15064.3(a), VMT—project-attributable auto travel amount and distance—is generally the most appropriate CEQA metric; automobile delay is not a significant impact except for roadway capacity projects (§ 15064.3(b)(2), where agencies retain metric discretion consistent with CEQA and other rules; § 21099(b)(2) adds "except in locations specifically identified in the guidelines, if any"). Land-use projects within 0.5 miles of an existing major transit stop or a stop on an existing high-quality transit corridor, or lowering area VMT versus existing conditions, generally qualify for a less-than-significant transportation-impact presumption ((b)(1)). The lead agency chooses the VMT method and should document and explain assumptions and model revisions in the environmental document; revisions must reflect professional judgment based on substantial evidence ((b)(4)). If existing models or methods cannot estimate project VMT, the lead agency may analyze it qualitatively; qualitative construction-traffic analysis may also suit many projects ((b)(3)).

Section 21099(b)(3) preserves CEQA review of potentially significant air quality, noise, safety and other transportation impacts (no presumption a project avoids them), while barring parking adequacy from supporting a significance finding under that section. Section 21099(b)(4) does not preclude local general plans, zoning, conditions or thresholds under police power or other separate authority, so local Level of Service (LOS) or turn-lane rules can still apply outside CEQA.

What does a traffic impact study include?

Virginia (24VAC30-155-60(B)–(D)) shows core VTIS elements:

  1. Scoping. VDOT scoping is mandatory at 1,000+ generator peak-hour trips and optional below (-60(B)). Road-measured limits—adjustable with VDOT, locality and applicant—scale by adjusted peak-hour trips (-60(C)(1)); a narrower minimum scope applies when meeting only the low-volume-road criterion (-40(A)(3)), unless VDOT directs otherwise (-60(C)(2)).
  2. Existing conditions. Preparers collect weekday 24-hour classification and AM/PM peak turning counts, normally avoiding holidays, unrepresentative periods, Fridays/weekends (unless VDOT or the locality requires them), summer near schools, adjacent-use skew and inclement weather. With VDOT approval, preparers may reuse their counts under 24 months old or VDOT count-program data (-60(D)(1)). Existing conditions cover lane-group LOS and VDOT-requested speed, crash or sight-distance checks; where significant walking, cycling or transit potential exists, analyze existing facilities/routes for existing conditions and add planned ones in future conditions (-60(C)(1)).
  3. Trip generation. Engineers use ITE's Trip Generation Manual—VDOT 8th Ed. unless approving alternate published/local rates (-60(D)(2)), FDOT 14-96.005(4)(a) 11th, and Maricopa latest unless TSMO approves other rates because ITE omits the use, data are limited or local rates differ (§ 4.1)—documenting internal-capture and pass-by reductions when used (VDOT -60(D)(3)(b): pass-by cuts adjacent-street additions, not driveway volumes).
  4. Horizons and analysis. Assign trips to nearby streets (-60(D)(4)). No-build forecasts combine background traffic and approved unbuilt projects; unless VDOT directs otherwise, preparers generally use historical compound growth where count history is extensive and capacity constraint is inappropriate (-60(D)(6)–(7)). Forecast each expected phase: under 500 peak-hour trips adds build-out or six years after start, whichever is later; higher tiers add post-build-out forecasts (-60(C)(1)). Rezonings conforming to an adopted plan reviewed under -30 with a technical traffic evaluation submitted to VDOT may use the under-500 scope (-60(C)(3)). Use Highway Capacity Manual methods for highway delay and LOS (-60(D)(8)). Test warrants where signals are expected, using the standard VDOT specifies. Document the method for any proposed transportation demand management measures (-60(C)(1), (D)(11)–(12)).

Traffic study review fees and timelines

Budget three lines: consultant work (scoping, counts, drafting, revisions); agency fees and clocks; and physical improvements.

Agency review fees

  • Virginia DOT (24VAC30-155-80, capped at $1,000/review by Va. Code § 15.2-2222.1(E)): Non-locality rezonings with a traffic impact statement pay one fee for initial and second reviews: $250 under -40(A)(3) or $1,000 otherwise ($0 for locality/public-agency filings and qualifying -40(C)(1) reuses). Fees recur if VDOT requests a third+ submission for unaddressed deficiencies (-80(C)(3)). See -80(C)(1) and § 15.2-2222.1(E) for non-locality comprehensive-plan fees and citizens'-organization exemptions.
  • Florida DOT (Fla. Admin. Code R. 14-96.004): Non-refundable standard Category C–G fees: $1,000 (C), $2,000 (D), $3,000 (E), $4,000 (F), $5,000 (G: 30,001+); if a new phase of an existing development needs a new permit, FDOT bases the fee on that phase (14-96.004(3)).
  • Austin, TX (Transportation Development Services, eff. October 1, 2026): Generally requires a TIA for site-plan, zoning or rezoning filings projecting >2,000 vehicular trips/day; the city sets analysis type from the filing and net new daily trips and may waive submission (§ 25-6-117). Site Plans: $3,680 scoping; $21,730–$74,720 (four review tiers, 2,000–40,001+ trips/day); $9,825 waiver/compliance; $6,140 Neighborhood Traffic Analysis. Zoning: $9,825 Zoning Traffic Impact Analysis (ZTA) Review; $2,700 ZTA Waiver/Compliance Check.

Agency review clocks (excluding engineer work)

  • Virginia DOT (Va. Code § 15.2-2222.1(B)–(C), 24VAC30-155-40(D)): For optional scoping below 1,000 generator peak-hour trips, VDOT replies within 30 days of request receipt for a meeting within 60 days (-60(B)(1)). Post-submittal: 45 days from proposal receipt for initial review, 120 for final review, and 45 days from impact-statement receipt to comment or schedule a meeting to be held within 60 days of proposal receipt. Under -40(D), written comments are due within 45 days of receipt if no meeting is requested or scheduled, or 120 otherwise; if missed, the locality may assume VDOT has no comments (§ 15.2-2222.1(C)).
  • Florida DOT (Fla. Admin. Code R. 14-96.007(2)–(4)): 30 days from submittal to request missing/corrected items; without a request, completeness backdates to original receipt ((2)(c)). Applicants have 60 days from receiving the completeness notice to respond unless it states otherwise (may request more time under (3)). Decision notice issues within 90 days of a complete application, receipt of all required information, or response-deadline expiration ((4)).
  • Maricopa County, AZ (MCDOT Manual §§ 1.2.3, 2.5): Generally 10 business days for waiver replies; the lead county department typically receives comments within 2–4 weeks of final sealed TIS/TS submittal (longer if neighboring jurisdictions are affected). Written TIS or TS approval lasts one year from issuance. If permitting has not started by then, ask TSMO whether current conditions require an update. Any development change (including land use or access) voids prior approvals and requires an updated study.

How a traffic study affects a land deal

Agencies may turn study recommendations into conditions on rezonings, site plans, plats, conditional use permits and driveway permits (land entitlement process), while some—like VDOT rezonings (24VAC30-155-40(D))—issue public-record comments. Under Fla. Admin. Code R. 14-96.007(8), FDOT permit terms bind future owners and occupants, and FDOT may require recording with the legal description for cross/joint access, future performance obligations (e.g., traffic-control devices) or other warranting conditions.

Fla. Stat. § 163.3180(5)(h)–(i) limits Florida mitigation. Localities that retain transportation concurrency must allow applicants for development-of-regional-impact development orders, development agreements, rezonings or other land-use development permits to offer in good faith a binding agreement to pay for or build their proportionate share. The share must be sufficient for a mobility improvement benefiting a regionally significant transportation facility. Localities may pool contributions for a planned improvement in a separate designated account. The project may proceed after payment or construction if all other local development requirements are met. Apply the proportionate-share formula only to significantly affected facilities; if deficient without the project's traffic (phase-specific definition in (5)(h)4.), remove the correction cost and assume the correction is in place. Exclude trips assigned to a toll-financed facility from trip forecasts; dollar-for-dollar credits apply to impact/mobility fees and other concurrency mitigation, reduced up to 20% by the project's share of added capacity or local ordinance, whichever gives greater credit ((5)(h)2.a.–e.). If a locality repeals concurrency for an alternative system complying with § 163.31801 (mobility-plan-and-fee-based or another system, including impact fees), it may not use that system to deny, time or phase site-plan, plat, final-subdivision or building-permit approvals (or equivalents) if the developer agrees to pay for the project's identified transportation impacts through the locality's funding mechanism. It cannot charge new development for existing deficiencies ((5)(i)). Localities need not approve projects failing local plan or land development rules for non-transportation reasons ((5)(h)3.).

Size land feasibility study and entitlement contingencies, confirming mitigation caps or turn-restriction exits before deposits go hard.

Screening traffic study risk before an offer

Four checks sharpen scoping (not replacing engineer review):

  • Road counts (AADT). Pull state DOT Annual Average Daily Traffic—like TxDOT's STARS II, showing mainlane and frontage-road counts separately; check year, station and direction (AADT guide).
  • Road ownership and access. Confirm ownership, driveway-permitting authority and road frontage vs. legal access. In Texas, owners or authorized representatives file Form 1058 where TxDOT permits state-highway driveways (Access Management Manual Ch. 2, Sec. 4), while some local agencies hold delegated authority (TxDOT must approve any state-highway drainage impacts from driveway installation before any local approval). Confirm spacing, median and study rules with the permitting agency.
  • Zoning and approvals. Check zoning, plats, title exceptions and case files for trip caps, cross-access easements, recorded DOT permits and prior-use trip credit.
  • Truck geometry. Trace the highway-to-dock route (industrial truck access guide): heavy trucks drive turning radii, auxiliary-lane warrants and capacity adjustments.

Check available zoning facts, acreage and FEMA flood zones in Pillar (Pillar for industrial); zoning and infrastructure layers need a paid plan or Pro trial, and coverage varies by dataset. Pillar does not estimate trips, run traffic studies, produce site plans or decide study requirements.

Quick answers

TIS vs. TIA: what is the difference?

TIS and TIA are common names for traffic impact studies and analyses. Virginia's rezoning rule distinguishes a local traffic impact statement from a VDOT traffic impact statement (VTIS).

When is a traffic impact study required?

For new or modified development under MCDOT jurisdiction, a full TIS is required at 100 or more trips in either peak hour. MCDOT can also require one below that threshold for the reasons above. See FDOT, VDOT and Austin above.

Who prepares and signs a traffic study?

Rules vary. In Virginia, the locality prepares the VTIS or has the owner or developer prepare it (-60(A)); see Florida (14-96.005(5)) and Maricopa (§ 2.4) seal rules above.

Can you get a traffic study waived?

Maricopa's § 1.2.3 waiver applies to a Traffic Statement, not a full TIS. Austin's director may waive TIA submission under § 25-6-117. Adverse effects still require mitigation, and the operating-level and public-safety limits still apply.

Does California's SB 743 end LOS studies?

No. Under 14 CCR § 15064.3(a), automobile delay is not a significant CEQA impact except for roadway capacity projects (§ 15064.3(b)(2)); local LOS or turn-lane rules can still apply outside CEQA under separate authority (§ 21099(b)(4)).