Geotechnical Report: When Required, Contents, Cost

A geotechnical report for land buyers: when the building code requires one, what it must contain, published costs and how to order borings before closing.

Pillar team12 min read

A geotechnical report (geotech or soils report) describes a site's soil, rock and groundwater and recommends a foundation type and design criteria. It draws on observations from borings, test pits or other subsurface exploration and necessary tests. When an investigation is required under the International Building Code, the permit applicant submits a written report to the building official at application.

By Pillar, a land research software company. Sources read November 24, 2026. General information, not engineering or legal advice: confirm what applies to your site with the building department and a licensed professional in your state.

What is a geotechnical report?

The International Building Code (IBC) calls the work a geotechnical investigation and the document "a written report of the investigations" (§ 1803.6). Santa Cruz County, California, calls it a "Geotechnical (Soils) Report." One soil boring test is the Standard Penetration Test, which ASTM D1586/D1586M-18e1 describes as driving a split-barrel sampler with a 140 lb hammer dropped 30 in.

When is a geotechnical report required?

The model rule is IBC section 1803. We read the 2024 edition on the International Code Council's viewer (Chapter 18). States and cities adopt their own editions and can amend them, so read the version your building department enforces.

The baseline and the waiver (§ 1803.2). Investigations "shall be conducted in accordance with Sections 1803.3 through 1803.5." The exception: the building official "shall be permitted to waive the requirement for a geotechnical investigation where satisfactory data from adjacent areas is available that demonstrates an investigation is not necessary for any of the conditions in Sections 1803.5.1 through 1803.5.6 and Sections 1803.5.10 and 1803.5.11."

Some of the conditions in § 1803.5 (2024 numbering):

  • Questionable soil or rock (§ 1803.5.2). Where the classification, strength, moisture sensitivity or compressibility of the soil or rock is in doubt, or a load-bearing value superior to the code's is claimed, the building official "shall be permitted to require" an investigation.
  • Expansive soil (§ 1803.5.3). "In areas likely to have expansive soil, the building official shall require soil tests to determine where such soils do exist." The 2024 section classifies soil as expansive when its plasticity index is at least 15 under ASTM D4318, more than 10% passes a No. 200 sieve and more than 10% is smaller than 5 micrometers under ASTM D6913, and its expansion index is greater than 20 under ASTM D4829. If the item 4 expansion-index test is conducted, the code does not require tests to establish items 1 through 3.
  • Groundwater (§ 1803.5.4). An investigation "shall be performed to determine" whether groundwater is above or within 5 feet below the lowest floor level, where that floor is below the finished ground level adjacent to the foundation, and whether the groundwater depth will affect design and construction.
  • Fill (§§ 1803.5.8 and 1803.5.9). An investigation shall be conducted where shallow foundations will bear on compacted fill material "more than 12 inches (305 mm) in depth," or on controlled low-strength material.
  • Seismic Design Categories C through F (§ 1803.5.11). For structures assigned to those categories, an investigation shall be conducted and shall evaluate slope instability, liquefaction, total and differential settlement, and surface displacement due to faulting or seismically induced lateral spreading or lateral flow.

Classification (§ 1803.5.1), deep foundations (§ 1803.5.5), rock strata (§ 1803.5.6), excavation near foundations (§ 1803.5.7), alternate setbacks and clearances from slopes (§ 1803.5.10) and the added items for Seismic Design Categories D through F (§ 1803.5.12) have their own subsections. The § 1803.2 exception does not list §§ 1803.5.7, 1803.5.8, 1803.5.9 or 1803.5.12.

What does a geotechnical report consist of?

Under § 1803.6 of the 2024 IBC, where investigations are required, "a written report of the investigations shall be submitted to the building official by the permit applicant at the time of permit application." The report "shall include, but need not be limited to," this information:

  1. A plot showing the location of the soil investigations.
  2. A complete record of the soil boring and penetration test logs and soil samples.
  3. A record of the soil profile.
  4. Elevation of the water table, if encountered.
  5. Recommendations for foundation type and design criteria, including but not limited to: bearing capacity of natural or compacted soil; provisions to mitigate the effects of expansive soils; mitigation of the effects of liquefaction, differential settlement and varying soil strength; and the effects of adjacent loads.
  6. Expected total and differential settlement.
  7. Deep foundation information in accordance with § 1803.5.5.
  8. Special design and construction provisions for foundations of structures founded on expansive soils, as necessary.
  9. Compacted fill material properties and testing in accordance with § 1803.5.8.
  10. Controlled low-strength material properties and testing in accordance with § 1803.5.9.

Do you need a soil test to build a house?

Under 2024 International Residential Code (IRC) § R401.4, if quantifiable data from accepted soil science methods indicate that expansive, compressible, shifting or otherwise questionable soils are likely at the site, the building official must decide whether to require a soil test. An approved agency must perform any required test using an approved method. Under Table R401.4.1(1), note b, if the building official finds that in-place soils with an allowable bearing capacity of less than 1,500 psf are likely at the site, a soils investigation must determine the allowable bearing capacity. When soil testing is performed and the seismic design category under § R301.2.2.1 is C or higher, the report must include the site class and short-period spectral response acceleration, SDS, determined under IBC § 1613. Assign the category under IRC Table R301.2.2.1.1.

Section R401.4.1 says that, in lieu of a complete geotechnical evaluation, the load-bearing values in Table R401.4.1(1) and the soil classifications in Table R401.4.1(2) "shall be assumed."

Is a soils report required in California?

The 2025 California Building Code, Title 24, Part 2, took effect January 1, 2026. Its § 1803 incorporates the 2024 IBC model provisions and includes California amendments for designated occupancies. Check the chapter's adoption matrix and the agency labels for the project.

California statutes also set report requirements for subdivisions (Government Code §§ 66490 and 66491) and for projects in mapped seismic hazard zones (Public Resources Code § 2697); read them with their waivers and definitions.

How to order a geotechnical investigation during a land deal

  1. Run the free desk checks. Read the soil survey; USDA's Web Soil Survey says "Onsite investigation is needed in some cases, such as soil quality assessments and certain conservation and engineering applications." Check FEMA's Flood Map Service Center (flood zone X) and the state geological survey's hazard maps where they exist (California's seismic hazard zones). Use the U.S. Fish and Wildlife Service's National Wetlands Inventory as a desk screen. It maps wetland type and extent using a biological definition. It does not establish government jurisdiction or regulatory coverage. A wetland delineation identifies where wetland boundaries lie. Use these to brief the engineer, not to skip the borings.
  2. Get the right to drill in writing. Standard Form 12-T, the vacant lot/land offer to purchase jointly approved by the North Carolina Bar Association and NC REALTORS (7/2026 revision, NC REALTORS' marked-up copy), shows the terms to look for. Under ¶ 2(b), the buyer or its agents or representatives may investigate the property at the buyer's expense, including getting reports on whether the soil is suitable for the buyer's intended use. Under ¶ 6(c), the seller must provide reasonable access through the earlier of closing or buyer possession but may limit or deny physical access until any agreed due diligence fee is delivered. Under ¶ 2(d), the buyer must promptly repair damage to the property from its activities or those of its agents and contractors at its own expense, except damage caused by accepted practices applicable to a North Carolina licensed professional performing reasonable appraisals, tests, surveys, examinations or inspections of the property. Under ¶ 2(e), the buyer must indemnify and hold the seller harmless for losses, damage, claims, suits or costs arising from contracts, agreements or injury to people or property resulting from the activities of the buyer or its agents or contractors relating to the property, except those arising from pre-existing property conditions or the seller's negligence or willful acts or omissions. The repair duty survives termination. The indemnity survives the contract and any termination. Ask your attorney to confirm that the signed agreement covers rig access, backfilling and restoration.
  3. Have utilities located before the rig arrives. 811 is "the free national before-you-dig service." Its page says to contact 811 or use your state 811 center's website "a few business days before you begin any digging" and to "wait a few days to allow utilities to respond to your request and ensure that all utilities have indeed responded to your request before breaking ground." Check state law for who must notify and when. Ask the drilling firm to make the request as required and confirm in writing before drilling that the wait period has passed, all notified utilities have responded, required markings are in place and any private lines have been located.
  4. Let the engineer set the scope. Under IBC § 1803.3.1, "The scope of the geotechnical investigation including the number and types of borings or soundings, the equipment used to drill or sample, the in-situ testing equipment and the laboratory testing program shall be determined by a registered design professional."
  5. Fit it inside the due diligence period. New Tech Engineering, a Pineville, North Carolina firm, publishes these timelines (page marked "Last Updated - October 23rd, 2025"; read November 24, 2026): "Small residential projects: 1-3 weeks," "Medium commercial projects: 3-6 weeks" and "Large industrial or infrastructure projects: 6+ weeks." Get a written delivery date and allow time to review the findings before your due diligence deadline. If the site is already under contract and the report will arrive too late, check the signed contract's notice and extension terms before the deadline.
  6. Ask what the findings change. Which foundation type and bearing capacity does the report recommend, and what settlement does it expect? How deep was groundwater, and does it affect below-grade levels or a stormwater pond?

How much does a geotechnical report cost?

New Tech Engineering's page gives this cost overview: "Residential projects: $2,000-$3,500" and "Commercial/industrial projects: $10,000-$50,000+." It says the cost "depends on project size, complexity, location, and depth of investigation." Ask for a written proposal that states the number and depth of borings, the laboratory tests and the report scope.

Who prepares a geotechnical report, and who can rely on it?

Under IBC § 1803.1, "Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional." The code's Chapter 2 defines that person by "the professional registration laws of the state or jurisdiction in which the project is to be constructed."

The Geoprofessional Business Association's notice, attached to a 2021 report posted by the City of Edgewood, Kentucky, says each report is prepared for one client, that anyone else should confer with the engineer who prepared it before relying on it, and that no one, the client included, should apply it to a purpose or project other than the one originally contemplated. It advises against relying on a report prepared for someone else, another project or another site, or completed before important project changes, unless the engineer who did the study says otherwise. Ask the firm that wrote the report whether it still covers your site, proposed design and intended use, and whether changes since the investigation call for an update. If you or your lender need to rely on it, ask the firm to confirm in writing who may rely on it and for what purpose.

Geotechnical report vs. soil survey, perc test, Phase I and topographic survey

  • Soil survey. USDA's published soil map data, read at a desk.
  • Perc test. A perc test measures how quickly water enters the soil. Some septic permitting authorities use it in site evaluation, while others use different soil evaluations. Check the permitting authority's requirements.
  • Phase I. A Phase I environmental site assessment uses records, interviews and a visual inspection to look for evidence of contamination. It generally does not include sampling for chemical analysis. EPA notes that some states may require sampling at this stage.
  • Topographic survey. A surveyor's map of ground elevations and surface features.

What to check before your due diligence deadline

Check the signed contract for access and due diligence deadlines. Under 2024 IBC § 1803.6, the permit applicant submits a written report to the building official at application when a geotechnical investigation is required.

  • Ask the seller for any existing geotechnical report, boring logs and grading or fill records, and who each report was written for.
  • Ask the building department which code edition it enforces, whether its permit files hold reports for the site or adjoining parcels, and whether it has waived investigations nearby under the § 1803.2 exception.
  • Record the desk findings in a desktop screening checklist, then carry the open questions into the land feasibility study and the land acquisition process.

Pillar shows a parcel's available zoning facts and acreage on the parcel record, and FEMA flood zones and the National Wetlands Inventory over parcel boundaries where those datasets cover the site; coverage varies by dataset (Pillar for multifamily). Those are mapped screens. Borings, bearing capacity and groundwater depth come from the investigation.

Quick answers

When is a geotechnical report required? Under the 2024 IBC, § 1803.2 says geotechnical investigations "shall be conducted in accordance with Sections 1803.3 through 1803.5," and § 1803.6 requires a written report where investigations are required. The building official may waive the investigation in the cases the § 1803.2 exception states. State laws and local ordinances can add triggers, such as California's subdivision and seismic hazard zone reports.

Who prepares a geotechnical report? A registered design professional in the cases IBC § 1803.1 lists. State registration law defines who qualifies.

How much does a geotechnical report cost? New Tech Engineering, a North Carolina firm, lists $2,000-$3,500 for residential projects and $10,000-$50,000+ for commercial/industrial projects on a page marked last updated October 23, 2025.

How long does a geotechnical report take? New Tech Engineering's October 23, 2025 page gives these examples: 1-3 weeks for small residential projects, 3-6 weeks for medium commercial projects and 6+ weeks for large industrial or infrastructure projects.

Can I use the seller's old geotechnical report? Ask the firm that wrote it whether the report still covers your site, design and intended use, and to confirm in writing who may rely on it and for what purpose. The association notice above tells anyone other than the client to confer with the report's engineer before relying on it. It tells everyone, including the client, to use it only for the original purpose and project.