Site Selection Criteria: Real Examples by Property Type

Site selection criteria are the requirements a site must meet. See published criteria from Wendy's, ALDI and three states, then build a screen.

Pillar team11 min read

Site selection criteria are the requirements a site must meet for a planned use. They split into must-haves that knock a site out (size, zoning that allows the use, access, utilities, no disqualifying flood or wetland area) and scored factors that rank the survivors (traffic or visibility, people or workers nearby, cost, time to approvals).

By Pillar, a land research software company. Sources read November 24, 2026. Each company's or agency's criteria below are its own, not an industry standard. General information, not legal advice; confirm zoning, title and utility questions with a licensed professional in your state.

What are site selection criteria?

They are a written list of what a site needs for one use, also called site selection factors or site requirements.

Which items are knockouts depends on the buyer: ALDI's page sets a daily traffic count above 20,000 vehicles as a minimum. Two of the published lists below check must-haves first. North Carolina's 2026 tax credit plan says applications "must meet all applicable threshold requirements to be considered for award and funding," then awards points. Tennessee's site certification page says Austin Consulting reviews all Step 1 applications using the information available to identify issues that would keep a site from completing the application process. If it finds no critical issues at Step 1, it emails the applicant a customized Step 2 application and the program's criteria and definitions. The page describes no point score. "Knockout" and "scored factor" are our labels.

Site selection criteria by property type: published examples

Retail and restaurant site selection criteria: Wendy's and ALDI

Wendy's. Its Preferred Site Criteria page lists demographic guidelines at 1 mile and 2 miles: residential population of 12K+ and 25K+ and daytime population or employees of 5K+ and 12K+. The same list gives "median income $40K – $75K" with no separate figure for each radius. Site attributes include "traffic counts 20K+", "drive-thru stack of 10+ cars" and "2+ miles from existing Wendy’s". Preferred land requirements include "freestanding lot size: 20K sq. ft. min." and "lot width: 120 ft. min". The page does not say which traffic measure or count year it means.

ALDI. Its property requirements list "2.5 acre pads for purchase and development" or "End-cap or inline space with minimum of 103’ of frontage", "±22,000 square feet with a minimum of 95 dedicated parking spaces", "Sites zoned to allow grocery use", "Daily traffic count in excess of 20,000 vehicles per day", "Dense trade area population within 3 miles" and "Signalized, full access intersection preferred".

See retail site selection for the trade-area work, outparcels and pad sites for shopping center pads and build to suit for building to a tenant's list.

Industrial site selection criteria: Louisiana and Tennessee certified sites

Louisiana and Tennessee certify industrial sites against published minimums. In Louisiana, the participant must obtain and maintain site control through ownership, an option or another legally binding agreement as a condition of certification. It must be possible to obtain the property free and clear of encumbrances. In Tennessee, a city or county government whose jurisdiction contains the site's boundaries, or a local or regional economic development organization formally recognized by the Tennessee Department of Economic and Community Development (TNECD), applies, and a privately owned site must be sponsored by one of them.

Louisiana. Louisiana Economic Development (LED) sets these criteria for certification on its Certified Industrial Sites page:

  • Size. "At least 25 contiguous, buildable acres, free of impediments to development such as existing structures not appropriate for future commerce, soil contaminants, wetlands, flood plain, protected species and/or cultural resources."
  • Zoning. "The site must be zoned or otherwise approved for industrial applications. If zoned, a zoning district description and map are required. Only sites suitable for industrial use will be considered. Sites adjacent to significant residential development or other land uses incompatible with industrial activities will not be considered."
  • Flood plain. At least 25 contiguous, buildable acres above the 100-year flood plain. Alternatively, the applicant may provide a formal cost estimate, construction plan and funding source for elevating construction footprints above it to meet FEMA standards.

For certification, LED's due diligence requirements include a Phase I Environmental Assessment, a Wetland and Stream Delineation, a Topographic Survey and 100/500-year Floodplain Designation, a Preliminary Geotechnical Investigation, a Cultural Resources Investigation and an Endangered Species Investigation, each with conditions stated on the page. Its program page and linked PDF give different Phase I age and assessment-standard requirements. Confirm the applicable requirements with LED before relying on an existing report.

LED's page sets further requirements, including water, sewer, road access, electricity, natural gas, price and site control.

Tennessee. Tennessee's Select Tennessee Certified Site program generally requires at least 20 net contiguous developable acres. Sites in Tier 3 or Tier 4 counties with at least 15 developable acres are also eligible if they are part of an industrial park and meet all other certification standards. TNECD's site certification page also says a certified site "has utilities on site or a formal extension plan in place."

Multifamily site selection criteria: North Carolina's 2026 tax credit plan

Federal law says the selection criteria in a qualified allocation plan for low-income housing tax credits "must include" project location (26 U.S.C. § 42(m)(1)(C)). The example below is one state's rulebook for tax credit applications. Market-rate developers set their own criteria; for zoning and density checks on a multifamily site, see multifamily development.

The North Carolina Housing Finance Agency's final 2026 Qualified Allocation Plan (Section IV(A)(1)) scores each site:

  • Site score. Up to 68 points: 10 for neighborhood characteristics, 46 for amenities and 12 for site suitability. "An application must have a minimum total score of 50 points." Each factor "will also serve as a threshold requirement; the Agency may remove an application from consideration if the site is sufficiently inadequate in one of the categories." The agency deducts up to 3 points when it finds a site unsuitable for housing. It can make that finding even if the site meets all site evaluation scoring criteria, regardless of whether it has the required zoning or local government support.
  • Site suitability. Four items worth 3 points each. The plan awards 3 points when the site has no Incompatible Use within its specified distances. Examples include an airport or operating landfill within half a mile of the approximate site center, and an active or inactive electrical utility substation within 250 feet of a proposed project building. The other three cover negative site features (the plan's list includes flood hazards, steep slopes and wetlands), visibility and traffic controls; read their conditions in the plan.

A second draft of the 2027 plan was posted when we checked; use the final plan for your cycle.

How to turn site selection criteria into a screen

This is site selection analysis: test every candidate against the same list, cheapest checks first.

1. Split the list. A knockout is a requirement where failing ends the review, like ALDI's "Sites zoned to allow grocery use". Use scored factors to rank the sites that pass. Define what earns a higher score for each factor. Write each knockout as a yes-or-no question with a source and, where applicable, a numeric cutoff.

2. Order the checks from cheapest to most expensive. Run the public-record screen first (desktop site screening checklist), then a drive-by, then paid studies on the sites that survive.

3. Match each criterion to a public source, and know what the source cannot tell you.

  • Size, shape and owner: the county parcel record and GIS. Sacramento County, California, for one, says "Assessor Maps are NOT surveys" and answers "Not necessarily" when asked whether parcels on its maps are legal parcels. Use a county's lines and acreage to screen, not to measure.
  • Zoning for the use: the zoning code and official map. Read the use table in the code itself to see whether the use is permitted, conditional or prohibited in that district, then check overlays. A future land use designation is a separate record (zoning vs. future land use).
  • Flood: FEMA's National Flood Hazard Layer. FEMA calls it "a geospatial database that contains current effective flood hazard data." The same page describes preliminary and pending flood hazard data separately, so check those too.
  • Wetlands: the National Wetlands Inventory. The Fish and Wildlife Service says its mapper makes no attempt "to establish the geographical scope of the regulatory programs of government agencies."
  • Traffic: the state DOT's counts. The Federal Highway Administration defines annual average daily traffic (AADT) as "The total volume of vehicle traffic of a highway or road for a year divided by 365 days." The glossary adds that it "is meant to represent traffic on a typical day of the year"; as we read that, it is not a peak-hour or turning count. Check the count's year and location (AADT guide).
  • People and workers: Census ACS and OnTheMap. The Census Bureau's estimates table lists 5-year ACS estimates as "Data for all areas" and 1-year estimates as "Data for areas with populations of 65,000+" (ACS guide). Census notes that the LEHD data behind OnTheMap "are based on tabulated and modeled administrative data, which are subject to error" (OnTheMap guide).
  • Utilities and trucks: written answers. Treat a mapped line near a parcel as a question, not a capacity commitment, and ask each provider in writing (will-serve letters). For industrial users, check the route as well as the driveway (truck access) and the yard rules (industrial outdoor storage).

4. Score the survivors. Use weights set in advance.

Worked example: a weighted scoring sheet for three hypothetical sites

Everything here is hypothetical: the sites, weights and scores are invented to show the arithmetic, and none is a real parcel or any company's standard.

A team seeking a drive-through restaurant pad drops Site D at the knockout stage because the zoning code prohibits the drive-through. It scores Sites A, B and C from 1 to 5 on five factors whose weights total 100%:

  • Traffic on the fronting road (30%): A 5, B 3, C 4
  • Residents in the trade area (25%): A 3, B 4, C 4
  • Access and signal (20%): A 4, B 5, C 2
  • Land cost (15%): A 2, B 4, C 5
  • Time to approvals (10%): A 3, B 2, C 5

Multiply each score by its weight, in the order listed, and add. Site A's traffic term is 0.30 × 5 = 1.50.

  • Site A: 1.50 + 0.75 + 0.80 + 0.30 + 0.30 = 3.65
  • Site B: 0.90 + 1.00 + 1.00 + 0.60 + 0.20 = 3.70
  • Site C: 1.20 + 1.00 + 0.40 + 0.75 + 0.50 = 3.85

C ranks first. Move 10 points of weight from land cost to traffic (40% and 5%) and A scores 3.95, C 3.75 and B 3.60, so A ranks first. Set the weights before you score, write down the rule behind each score, and treat a gap this small as a tie to settle on site.

The site selection process, step by step

  1. Define the requirements. Write the knockouts and scored factors, with numbers.
  2. Set the search area. A market, a trade area or a drive time.
  3. Build the long list. Every parcel that could pass the knockouts, listed or not (finding off-market development land).
  4. Run the desktop screen. Knockouts first, from public records.
  5. Shortlist and visit. Score the survivors and drive them.
  6. Run due diligence under site control. Tie up the site with an option or contract, then order the studies (land feasibility study; land acquisition process).
  7. Seek approvals. See the land entitlement process.

Software can speed up steps 3 and 4; see site selection software for land development.

Site selection for a land buyer: what to check before an offer

  • Parcel record, deed and zoning code. Compare the acreage and owner name on the record and the deed, and save the code's use table row with the date you read it.
  • Title commitment and survey. Read the Schedule B exceptions and plot the easements against the layout your criteria assume (title commitment; ALTA survey).
  • Contract. List the knockouts a desktop screen cannot close, such as utility capacity, wetlands and soils, and ask your attorney to fit the due diligence period to them.

For the first pass, Pillar's property search shows a parcel's available zoning facts and acreage and mapped FEMA flood zones. Coverage varies by dataset; confirm use rules in the code itself.

Quick answers

What are site selection criteria? The requirements a site must meet for a planned use: knockouts that end the review and scored factors that rank the sites left.

What are the factors to consider when selecting a site? Size, zoning for the use, access, utilities, flood and wetland area, traffic or visibility, people or workers nearby, cost and time to approvals. Which are knockouts depends on the use.

What is the site selection process? Seven steps: requirements, search area, long list, desktop screen, shortlist and visits, due diligence under site control, approvals.

What is site selection analysis? Testing each candidate against the same criteria, knockouts first, then scoring the survivors with weights set in advance.

What are commercial site selection criteria? Each company sets its own. Wendy's page lists "traffic counts 20K+". ALDI's page lists 2.5-acre pads for purchase and development or end-cap or inline space with at least 103 feet of frontage. It also requires a daily traffic count above 20,000 vehicles.

What are industrial site selection criteria? Each user or program sets its own. Louisiana Economic Development's size criterion for certification is "At least 25 contiguous, buildable acres, free of impediments to development such as existing structures not appropriate for future commerce, soil contaminants, wetlands, flood plain, protected species and/or cultural resources." Tennessee's Select Tennessee Certified Site program generally requires at least 20 net contiguous developable acres. Sites in Tier 3 or Tier 4 counties with at least 15 developable acres are also eligible if they are part of an industrial park and meet all other certification standards.

How do you weight site selection criteria? Give each scored factor a share of 100%, score every site on the same scale, multiply and add. Set the weights first, because changing them can change the ranking.