Data Center Site Selection: Criteria and Public Checks

Data center site selection starts with power, fiber, water, hazards, zoning and incentives. See where to check each, with a Loudoun County, VA example.

Pillar team12 min read

Data center site selection is the process of choosing land for a data center by screening each candidate site for electric power and grid capacity, fiber, water for cooling, natural hazards, zoning, tax incentives, and the size and shape of the land.

Use public maps and records to shortlist sites. Then confirm capacity and timing with the utilities and carriers, verify the approval path with local staff, and test the usable area against a survey.

By Pillar, a land research software company. Sources read November 26, 2026. The zoning and tax examples are Loudoun County's and Virginia's; other places differ. General information, not legal, tax or engineering advice: confirm with a licensed professional in your state.

What is data center site selection?

It is the same two-pass work as any site selection: a desktop screen that knocks sites out from public records, then written confirmations on the sites that survive. In its 2024 study, Virginia's Joint Legislative Audit and Review Commission (JLARC) called "Access to power and large, flat areas of land" key requirements for data centers.

Data center site selection criteria, and where to check each

  • Power. The utility confirms capacity. Dominion Energy's data center requests page, checked November 26, 2026, tells applicants to confirm on its map that the site is in its service territory. The page says new data centers with expected loads of less than 50 megawatts "can frequently be connected by utilizing existing electric distribution infrastructure." Serving loads of more than 50 megawatts "will most likely require the extension of transmission lines and the construction of a new substation." Ask the utility serving your site.
  • Transmission maps. A public line map shows where a line is, not what it can serve. The Homeland Security Digital Library says DHS-managed HIFLD Open shut down in August 2025. The library preserves a collection of its open datasets. Esri's Federal User Community publishes a U.S. transmission-line archive on ArcGIS Hub using U.S. government data. It was last updated September 30, 2024, describes operating voltages from 69 to 765 kV, and includes underground lines where source data were available. Ask the utility about available capacity.
  • Fiber. The FCC map shows provider-reported mass-market fixed broadband availability by location and modeled mobile coverage. For data center fiber, ask carriers for routes, physical diversity, construction timing and a written quote.
  • Water. Virginia's 2024 JLARC study says water demand depends on facility size, computing density and cooling design. Check the serving utility's map, then provide your expected peak water demand and wastewater discharge.
  • Flood and earthquake hazard. FEMA calls the National Flood Hazard Layer "a geospatial database that contains current effective flood hazard data"; the same page describes preliminary and pending data separately. The USGS says its National Seismic Hazard Models "forecast where, how much, and how often the ground could shake from potential future earthquakes."
  • Land. Take acreage and shape from the parcel record, then the survey, and subtract what setbacks and buffers remove (see the 200-foot rule below). If one parcel is too small, see land assemblage.

Data center zoning: how Loudoun County, Virginia writes the rule

Where it is allowed. The principal use tables in Loudoun County's Zoning Ordinance carry a key that reads "P = Permitted | S = Special Exception | M = Minor Special Exception | blank cell = Prohibited". The Data Center row is "S" in the OP, IP, GI and MR-HI districts (Table 3.02.05-1, amended March 18, 2025) and in the legacy PD-RDP and CLI districts (Table 3.02.02-1). It is blank in that table's other districts and in every district of Tables 3.02.01-1 (urban and suburban), 3.02.03-1 (transition, rural and JLMA) and 3.02.04-1 (legacy transition, rural and JLMA).

What "S" requires. Under Section 10.11.01, the Planning Commission holds a public hearing and forwards a recommendation of approval or denial. The Board of Supervisors then holds its own public hearing and may impose conditions.

Sites handled separately. For a site with an existing approval or an application accepted by February 12, 2025, ask the county whether Table 3.02.05-1's notes or the March 18, 2025 resolution apply. For a parcel in the Route 28 Tax District or with a legacy Route 28 Corridor overlay election, ask the Zoning Administrator whether Sections 1.02.K or 5.09 apply and which ordinance and use table govern.

Use standards (§ 4.06.02). At site-plan filing, submit all materials needed to assess § 4.06.02 compliance. For conditional or final site-plan approval, the applicant must show compliance with § 4.06.02 and all other applicable zoning ordinance standards. These two apply when the site is adjacent to property with existing residential development, an approved concept development plan, plat or plan showing residential development, or a zoning district permitting residential uses:

  • Setbacks (D.7). Structures must be set back at least 200 feet from the common property line. D.7.a requires parking to be at least 50 feet from the common property line. The natural-screening provision requires existing forest and other natural screening within 50 feet of the lot line to remain undisturbed or be enhanced under Chapter 7. If no forest or natural screening exists, the same parking setback applies, and the site must provide a berm at least 10 feet high, with slopes no steeper than 2:1 on either side of the crown edge and 10-foot-tall fencing and plantings on top. D.7 also applies when a principal arterial or lesser designated roadway, per the Countywide Transportation Plan, separates the two properties.
  • Generators (D.8). Subject to Commonwealth regulations or permits issued for the property, generator testing is limited to between 11:00 a.m. and 5:00 p.m. from October 1 to April 30. The May 1 to September 30 window starts at 5:00 p.m. The online text prints its end as "7:00 m."; the county's Phase 2 draft proposes inserting "a." to read "7:00 a.m.", so confirm the current rule with zoning staff. Except for testing or commissioning, generator use is limited to backup or emergency use.

Other standards to check in the code: noise studies (§ 7.05.03.G), acoustical screening (§ 4.06.02.D.10), façades (C), mechanical equipment location and screening (D.2), building height changes and step-backs (D.7.c–d), lighting (D.9), and landscaping and buffers (D.11).

The county is reviewing these standards. Its Phase 2 page anticipates a Planning Commission public hearing in February 2027 and a Board of Supervisors public hearing in July 2027.

On November 17, 2026, Loudoun adopted a pause on Board action for certain data center and substation applications. Developers may still submit applications, and staff still reviews them and schedules Planning Commission hearings. Ask county staff whether the pause affects your special exception and when the Board can hear it.

Data center tax incentives: Virginia's sales and use tax exemption

Virginia Code § 58.1-609.3(18) exempts from Virginia's retail sales and use tax, including the local tax authorized by §§ 58.1-605 and 58.1-606, from July 1, 2010 through June 30, 2035, subject to the separate extension rules in subdivision 19, "computer equipment or enabling software purchased or leased for the processing, storage, retrieval, or communication of data," including servers, routers, connections and other enabling hardware, and chillers and backup generators used or to be used in operating the exempt equipment. A data center includes other data center facilities in the same locality under common ownership or affiliation with its operator. The equipment or software must be purchased or leased for use in a data center that:

  1. is located in a Virginia locality;
  2. results in a new capital investment on or after January 1, 2009, of at least $150 million; and
  3. results in the creation on or after July 1, 2009, of at least 50 new jobs by the data center operator and the tenants of the data center, collectively, associated with its operation or maintenance, provided the jobs pay at least one and one-half times the prevailing average wage in that locality.

The jobs requirement drops to 10 if the data center is in a distressed locality when the memorandum of understanding is executed, and the investment requirement drops to $70 million for data centers that qualify for the reduced jobs requirement. From and after July 1, 2023, a locality is distressed when its annual unemployment rate and its poverty rate meet this test: each rate exceeds its corresponding statewide average for the most recent calendar year for which that measure is available, using the final statewide average for unemployment.

The exemption applies to the operator and the tenants if they collectively meet the section's requirements. Before claiming it, the claimant must enter a memorandum of understanding with the Virginia Economic Development Partnership Authority (VEDP) that covers, at a minimum, how investment and jobs are determined, the timeline, the repayment obligations if the goals are not achieved, and any conditions under which repayment may be required. The operator may sign the required memorandum on behalf of itself and its tenants. While claiming the exemption, the operator must file an annual report with VEDP for itself and any participating tenants, following VEDP's procedures and prescribed format. Report employment levels, capital investments, average annual wages, qualifying expenses, tax benefit and other information VEDP requires. The exemption also covers qualifying computer equipment or enabling software bought or leased to upgrade, supplement or replace computer equipment or enabling software bought or leased in the initial investment. The exemption does not apply to "general building improvements or other fixtures" or to other taxable software sold or leased separately from the equipment.

The Virginia Department of Taxation's 2026 Legislative Summary (July 6, 2026) says Item 1(N)(5) of the 2026 Appropriation Act directs the Joint Subcommittee on Tax Policy to study the exemption and report its recommendations by December 15, 2026. Recheck the statute after that date.

Worked example: screening a hypothetical Loudoun County site

This site is hypothetical: a vacant tract of 40 to 80 acres, zoned IP, with houses along one side.

  1. Ordinance and district. Confirm the district on the county's zoning map (WebLogis), and ask the Zoning Administrator which ordinance and use table govern the parcel.
  2. Approval type. Table 3.02.05-1 shows "S" for IP, so plan for a special exception with two public hearings. Ask county staff when the Board can hear it. A blank cell in the applicable use table means the use is prohibited under the table's key; changing the district is a rezoning.
  3. Neighbors. The houses trigger the 200-foot structure setback. Assume a straight 1,000-foot shared boundary and a rectangular strip. Our illustrative setback calculation is 200 × 1,000 = 200,000 square feet, or about 4.6 acres. Check C.1, D.7.c–d, D.2.b, D.8 and D.10.b.
  4. Flood. Open the parcel in FEMA's layer (Flood Zone X).
  5. Power. Measure to the nearest mapped line and note the layer's 2024 date. Then confirm the serving utility and ask it about the megawatts you need.
  6. Incentive. Compare the planned investment and jobs with the statute's three conditions. The statute requires the memorandum before any claim; this screen does not show that a project qualifies.

What stops it: a blank cell in the applicable use table, or a utility answer that does not fit the schedule. What advances it: an "S" district, room for the setbacks, a written utility response, and a date when the Board can hear the application.

Powered land: what to verify before an offer

If a listing calls the site "powered land," ask for the utility's written response. Check the MW available at each stage, the service dates, any conditions or expires-by dates, and who pays for extensions and other required work.

Pillar shows a parcel's acreage, available zoning facts and mapped FEMA flood zones on a free account (Pillar for data centers). Transmission line and substation layers need a paid plan or an active Pro trial, coverage varies by dataset, and a mapped line does not confirm capacity, so ask the utility and check each line's source date.

Quick answers

How are data center sites selected? In two passes. Public maps and records shortlist the sites. Then the utilities and carriers confirm capacity and timing, local staff confirm the approval path, and a survey tests the usable area.

What are the key criteria for selecting a data center site? Power, land, fiber, cooling water, flood and seismic hazard, zoning and tax treatment. JLARC names "Access to power and large, flat areas of land" as key requirements.

What kind of zoning is needed for a data center? It depends on the local code. Loudoun County's principal use tables mark Data Center "S" (special exception) in OP, IP, GI, MR-HI, PD-RDP and CLI. Ask the county which ordinance and use table govern the parcel.

How much land does a data center need? Start with the facility's requirements and check local lot and district rules. Loudoun's § 4.06.02 gives no data-center-specific minimum lot size. Table 2.06.02-1 sets a 1-acre minimum IP lot size, exclusive of major floodplain, subject to modification under § 10.10.04.C. Use the survey to test what fits after setbacks, buffers and easements. An initial IP district must be at least 10 acres (§ 2.06.02.A.2). The Board may approve a rezoning to add at least 1 acre if the addition meets § 2.06.02 and the Board finds it abuts an existing IP district or lies across a road of at most four lanes from it, and connects to it by road, pedestrian and bicycle networks.

Does a nearby transmission line mean the site has power? No. A map shows a line's location. The utility confirms capacity and timing.

How long does it take to get power to a data center? Dominion's page, checked November 26, 2026, says it depends on customer needs and location. New data centers with expected loads under 50 MW can often use existing distribution. Those projects "typically require 1-2 years to complete" from initial planning conversations. Above 50 MW of expected load, Dominion says a new center will most likely need transmission extensions and a new substation. It gives no time range.

What should you ask about a site marketed as powered land? Ask for the utility's written response: the MW available at each stage, the service dates, any conditions or expires-by dates, and who pays for extensions and other required work.